  • modernization of the 110 kV Substation Teofilów, in terms of replacement of HV equipment, for Łódź Teren Utility,
  • modernization of the 110/30/15 kV Substation Bukowiec, in terms of the development to \"H 4\" system, for ENION in Częstochowa,
  • reconstruction and modernization of the 110/15 kV Substation Węgierska Górka, for ENION in Bielsko Biała,
  • modernization 110 kV substation for Stalowa Wola Power Plant,
  • modernization of the 110 kV Substation Gdańsk II, for ENERGA in Gdańsk,
  • construction of electric power offtake in the gas block of Starachowice Heating and Power Plant, for the commission of Elektrobudowa S.A. in Katowice.